ITEM TITLE:
Title
Consider approving plans and specifications for the Gore Blvd. Waterline and Sewerline Reconstruction - 82nd ST to 67th ST- Project No. EN1208A and authorizing staff to advertise for bids.
body
INITIATOR: Director of Engineering, Joseph Painter, P.E.
STAFF INFORMATION SOURCE: Director of Engineering, Joseph Painter, P.E.
BACKGROUND: Gore Blvd. Waterline and Sewerline Reconstruction - 82nd ST to 67th ST- Project No. EN1208A includes the construction of approximately 5200-LF of 12-inch and 315-LF of 8-inch waterlines and approximately 900-ft of 12-inch and 8-inch sanitary sewer lines on W. Gore Blvd. from 82nd ST to 67th ST using a combination of open trench and directional drill construction techniques. The Engineer’s Estimated Construction Cost for this project is $1,638,723.90. The construction time for the project is estimated to be 180 calendar days.
EXHIBIT: Plans and specifications are on file in the Engineering Division Office
KEY ISSUES: None
FUNDING SOURCE: 2015 CIP
STAFF RECOMMENDED COUNCIL ACTION: Approve plans and specifications for the Gore Blvd. Waterline and Sewerline Reconstruction - 82nd ST to 67th ST- Project No. EN1208A and authorizing staff to advertise for bids.