Consider approving Project EN2107 On-call Citywide Sidewalk Contract to select a contractor to construct sidewalk around the city and authorizing staff to advertise for bids.
body
INITIATOR: Director of Engineering, Joseph Painter
STAFF INFORMATION SOURCE: Director of Engineering, Joseph Painter
BACKGROUND: Project EN2107 On-call Citywide Sidewalk Contract is a requirements (as-needed) contract for Sidewalk installation, repair and replacement. A work order will be issued to the contractor for a scope of work defined in the work order. The unit prices will be the method used to pay for the work in each work order issued. Total anticipated contract period will be for two years with a total amount not to exceed $2,000,000. The initial phase of the project contract will be for one year or $1,000,000, whichever comes first, at which point the Contractor’s performance will be evaluated and, if deemed satisfactory, the contract may then be renewed for the additional one-year period upon agreement of both parties.
EXHIBIT: Project EN2107 On-call Citywide Sidewalk Contract
KEY ISSUES: None
FUNDING SOURCE: LETA, 2019 CIP
STAFF RECOMMENDED COUNCIL ACTION: Approve Project EN2107 On-call Citywide Sidewalk Contract to select a contractor to construct sidewalk around the city and authorizing staff to advertise for bids.