Consider approving offsite improvement construction plans for a water line and fire hydrants to serve Marie Detty - Youth Shelter and Office, to be located at 4521 SW Lee Blvd subject to the conditions listed.
body
INITIATOR: Christy Jame, Planning Director
STAFF INFORMATION SOURCE: Kameron Good, Senior Planner
BACKGROUND: Construction plans have been submitted to extend approximately 493 linear feet of 12-inch water line, approximately 644 linear feet of 8-inch water line, and two fire hydrant to serve a new 13,967 square foot Marie Detty - Youth Shelter and Office. The general contractor is Joe D. Hall, LLC, the architect is Studio Architecture, P.C. and the consulting engineer is BWR Design Group.
Staff has reviewed and approved the building permit plans. The water line plans have been reviewed by the Public Utilities Department and has recommended approval subject to the redlined conditions. The redlined plans are attached as an exhibit.
The City Planning Commission made a recommendation of approval on December 12, 2024 with a vote of 8-0.
EXHIBIT: Plans and Profiles Red Lined with Conditions
CPC Minutes 12-12-2024
KEY ISSUES: N/A
FUNDING SOURCE: N/A
CPC RECOMMENDED COUNCIL ACTION: Approve for the offsite improvement construction plans for a water line and fire hydrants to serve Marie Detty - Youth Shelter and Office, subject to the conditions listed.