Title: Consider acknowledging receipt of permit number WL000016240030 for the construction of PU2308 Map 09 Waterlines Project from the Oklahoma Department of Environmental Quality.
Attachments: 1. WL000016240030 Map 09 Permit
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

ITEM TITLE:

Title

Consider acknowledging receipt of permit number WL000016240030 for the construction of PU2308 Map 09 Waterlines Project from the Oklahoma Department of Environmental Quality.

body

INITIATOR:  Rusty Whisenhunt, Director of Public Utilities

 

STAFF INFORMATION SOURCE:  Rusty Whisenhunt, Director of Public Utilities

 

BACKGROUND: On January 19, 2023, the City of Lawton was granted permit no. WL000016240030 from the Oklahoma Department of Environmental Quality for the construction of PU2308 Map 09 Waterlines Project. The permit approves construction of 35,350 linear feet of eight (8) inch PVC potable water line, 720 linear feet of ten (10) inch PVC potable water line and all appurtenances. A condition of the permit is that it must be noted in the minutes of the next regular meeting on the Lawton City Council. This permit has been delayed getting onto the council agenda due to interior staffing changes.

 

EXHIBIT:  ODEQ Construction Permit

 

KEY ISSUES:  None

 

FUNDING SOURCE:  N/A

 

STAFF RECOMMENDED COUNCIL ACTION:  Acknowledge receipt of permit number WL000016240030 for the construction of PU2308 Map 09 Waterlines Project from the Oklahoma Department of Environmental Quality.