Title: Consider approving a Change Order 1 on Project PR2309-Elmer Thomas Park Aquatic Center to reduce the contract amount by $705,049.00, based on the Value Engineering review.
Attachments: 1. Elmer Thomas Aquatic Center Value Engineering 8.14.24, 2. PR2309 Amendment Change Order No-1.docx, 3. COL_Aquatic_Center_CD_20240909 10, 4. Final Lawton Aquatics Schematic Presentation 5, 5. Page 9 from Final Lawton Aquatics CD Presentation 24.07.22, 6. Page 14 from Final Lawton Aquatics CD Presentation 24.07.22
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
ITEM TITLE:
Title
Consider approving a Change Order 1 on Project PR2309-Elmer Thomas Park Aquatic Center to reduce the contract amount by $705,049.00, based on the Value Engineering review.
body
INITIATOR: Mike Jones, Interim Director of Engineering

STAFF INFORMATION SOURCE: Mike Jones, Interim Director of Engineering

BACKGROUND: On September 10th, 2024, Council approved a contract with Miller-Tippens Construction in the amount of $19,900,000.00. Per Council direction, the architect and staff met with the contractor to identify potential cost savings within the project plans by performing a Value Engineering Review which resulted in a potential cost savings to the project of approximately $967,106.00. Based upon the review, considerations were made for adjustments to the project scope resulting in Change Order 1.

The items to be included in Change Order 1 are VE#2A which is to remove all stabilization, curb and gutter, and paving at all areas on site in the amount $644,544 and VE#3 to install insulated wood stud interior wall framing in lieu of scheduled CMU in the amount $60,505. To clarify, the gravel parking lot option was one of the options to consider however that is not part of the change order. If the change order is approved, paving would be accomplished by the City under a separate contract. The total cost savings to this project for these two items is $705,049.00 and the new contract amount will be $19,194,951.00.

The other identified items are pending further review. These items include eliminating air conditioning from the restrooms/changing rooms and changing the building pad requirements based on existing soil conditions. It is anticipated another Change Order will be brought to the Council after additional review is complete.


EXHIBIT: Proposed Change Order 1

KEY ISSUES: Unknown

FUNDING SOURCE: Project Account 4400000-541...