Title: Consider directing the City Manager to proceed with the construction of the Elmer Thomas Aquatics Center Parking Lot by authorizing staff to go out for bid on said project (PW2502)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

ITEM TITLE:

Title

Consider directing the City Manager to proceed with the construction of the Elmer Thomas Aquatics Center Parking Lot by authorizing staff to go out for bid on said project (PW2502)

body

INITIATOR:  Michael Watrous, Public Works Director

 

STAFF INFORMATION SOURCE:  Michael Watrous, Public Works Director

 

BACKGROUND: At the 11 February Streets and Bridges Committee, priority was given to the Elmer Thomas Aquatics Center Parking Lot construction with the remainder of the FY25 funds dedicated to the Streets and Bridges Committee. This parking lot was taken off from the initial Aquatics Center construction as, after review, it was determined the project could be done at a lower cost being a separate project, bid on by local contractors.

 

EXHIBIT:  N/A

 

KEY ISSUES:  N/A

 

FUNDING SOURCE:  Streets and Traffic Control Repair and Maintenance Account 1005502-51020, Current balance $2,326,268, Estimated cost $500,000.

 

STAFF RECOMMENDED COUNCIL ACTION:  Directing the City Manager to proceed with the construction of the Elmer Thomas Aquatics Center Parking Lot by authorizing staff to go out for bid on said project (PW2502)