ITEM TITLE:
Title
Consider acknowledging receipt of permit number WL000016240751 for the construction of PU2403 Map 10 & PU2408 Map 39 Waterline Replacement Projects from the Oklahoma Department of Environmental Quality.
body
INITIATOR: Rusty Whisenhunt, Director of Public Utilities
STAFF INFORMATION SOURCE: Rusty Whisenhunt, Director of Public Utilities
BACKGROUND: On March 28, 2023, City Council was given a presentation on Public Utilities’ Water and Wastewater system conditions and a plan of improvements with a means of funding the improvements. On June 27, 2023, City Council approved the Master Service Agreement with Jacobs Engineering Group, INC. Amendment No. 3 to the MSA was approved by Council on September 26, 2023, and included a scope of services and fee to provide Professional Engineering services for water system rehabilitation defined in work package #3. The Plans and Specifications and authorization for advertisement was approved by council on June 25, 2024.
A construction contract for PU2403 Map 10 Waterline Replacement project was awarded to Southwest Water Works, LLC, in the amount of $6,469,870 by City Council on August 27, 2024.
A construction contract for PU2408 Map 39 Waterline Replacement Project was awarded to Stampede Utility Construction, LLC, in the amount of $6,425,000 by City Council on September 10, 2024.
The project will benefit The Citizen by preventing outage and providing safe drinking water to meet the goals of Safe Community and Our Pursuit of Excellence in the True North Culture.
EXHIBIT: ODEQ Construction Permit
KEY ISSUES: None
FUNDING SOURCE: N/A
STAFF RECOMMENDED COUNCIL ACTION: Acknowledge receipt of permit number WL000016240751 for the construction of PU2403 Map 10 & PU2408 Map 39 Waterline Replacement Projects from the Oklahoma Department of Environmental Quality.