Title: Consider approving Change Order No. 2 for 4X Construction Group, LLC on Engineering Project PW2101-Landfill Cells 6 & 7 in the amount $37,700.00.
Attachments: 1. COW Cells 6 7 PW 2101 Change Order No. 2_signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

ITEM TITLE:

Title

Consider approving Change Order No. 2 for 4X Construction Group, LLC on Engineering Project PW2101-Landfill Cells 6 & 7 in the amount $37,700.00.

body

INITIATOR:  Sneha Dongre, Associate Civil Engineer/Michael Watrous, Public Works Director

 

STAFF INFORMATION SOURCE:  Sneha Dongre, Associate Civil Engineer/Michael Watrous, Public Works Director

 

BACKGROUND: On May 14, 2024 Council awarded the construction contract for Project PW2102 - Landfill Cells 6 & 7 to 4X Construction Group, LLC.  The project consists of expansion of two (2) new cells at the existing landfill site.                                                                        

 

On August 27, 2024 Council approved Amendment No. 1 & Change Order No. 1 consisting of additional quantities for demucking, intercell berm, 8-inch ball port valve at intercell berm, and additional general fill associated with backfilling. The original contract amount was $3,841,081.25.  The approval of Change Order No 1 added an additional cost of $199,526.55, making the new contract amount total $4,040,607.80.  No additional work days were requested with this change order.

 

Change Order No. 2 accounts for additional 1-foot protective cover (imported from off-site borrow source) required to be placed on top of the west side slope of Cell 7 at the City of Lawton landfill.  This change order will add an additional cost of $37,700.00, making the new contract amount total $4,078,307.80.  No additional work days are requested with this change order.

 

EXHIBIT:  Change Order No. 2

 

KEY ISSUES:  None

 

FUNDING SOURCE:  Funding for the Landfill in the amount of $7M is obtained through the $30M loan.

 

STAFF RECOMMENDED COUNCIL ACTION:  Approve Change Order No. 2 for 4X Construction Group, LLC on Engineering Project PW2101-Landfill Cells 6 & 7 in the amount of $37,700.00.