Consider approving Amendment No. 1 to the Standard Form of Agreement between the City of Lawton and GH2 Architects, LLC. to provide professional architectural and engineering services to design selected schematic design plan on Project PR2310 East Side Park and Lee West Park Improvements.
body
INITIATOR: Michael Jones, Interim Director of Engineering
STAFF INFORMATION SOURCE: Michael Jones, Interim Director of Engineering
BACKGROUND: On January 22, 2024, Council approved a Standard Form of Agreement with GH2 Architects, LLC. in the amount of $45,400.00 to provide initial services/schematic design architectural services for Project PR2310 East Side and Lee West Park Improvements. The initial services were focused on constructing two new splash pad structures at East Side and Lee West Park that will include construction of a new parking lot, restroom facilities, and sidewalks.
Amendment No. 1 includes additional services for Schematic Design, Design Development, Construction Documents, Bidding and Construction Phase services on Project PR2310 for East Side and Lee West Park Improvements as presented in the Initial Services phase item 1.2 in the contract. Total fees included in Amendment No. 1 equal $101,950.00. This makes the total contract amount including original amount of $45,500 to be $147,450.00.
EXHIBIT: Amendment No. 1 PR2310 East Side and Lee West Park Improvements
KEY ISSUES: None
FUNDING SOURCE: Propel
STAFF RECOMMENDED COUNCIL ACTION: Approve Amendment No. 1 to the Standard Form of Agreement between the City of Lawton and GH2 Architects, LLC. to provide professional architectural and engineering services to design selected schematic design plan on Project PR2310 East Side Park and Lee West Park Improvements.