Title: Consider approving Amendment No. 1 & Change Order No. 1 for 4X Construction Group, LLC on Engineering Project PW2101 - Landfill Cells 6 & 7.
Attachments: 1. COW Cells 6 7 PW 2101 Change Order No. 1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

ITEM TITLE:

Title

Consider approving Amendment No. 1 & Change Order No. 1 for 4X Construction Group, LLC on Engineering Project PW2101 - Landfill Cells 6 & 7.

body

INITIATOR:  Sneha Dongre, Associate Civil Engineer / Michael Watrous, Public Works Director

 

STAFF INFORMATION SOURCE:  Sneha Dongre, Associate Civil Engineer / Michael Watrous, Public Works Director

 

BACKGROUND: On May 14, 2024 Council awarded the construction contract for Project PW2101 - Landfill Cells 6 & 7 to 4X Construction Group LLC.  The project consists of expansion of two (2) new cells at the existing landfill site.                                                    

 

Amendment No. 1 & Change Order No. 1. Accounts for demucking, intercell berm, 8-inch ball port valve at intercell berm, and additional general fill associated with backfilling. The original contract amount was $3,841,081.25.  This change order will add an additional cost of $199,526.55, making the new contract amount total $4,040,607.80.  No additional work days are requested with this change order.

 

EXHIBIT:  Amendment No. 1 & Change Order No. 1

 

KEY ISSUES:  N/A

 

FUNDING SOURCE:  Funding for the Landfill in the amount of $7M is obtained through the $30M loan.

 