ITEM TITLE:
Title
Consider approving offsite improvement construction plans for an extension to SW Gilbert Gibson Rd, water line, and sanitary sewer to serve Fisher 59 and future development within the Airport Industrial area, subject to the conditions listed.
body
INITIATOR: Christine James, Planning Director
STAFF INFORMATION SOURCE: Kameron Good, Senior Planner
BACKGROUND: Construction plans have been submitted to extend SW Gilbert Gibson Rd, approximately 2,900 linear feet of 12-inch sanitary sewer line, and approximately 1,683 linear feet of 12-inch water sewer line to serve a Fisher 59 and future development within the Airport Industrial area. The consulting engineer is Joseph Parsley with Carlson Consulting Engineering.
Staff has reviewed the plans and recommends approval subject to the following conditions:
1. Obtain an ODEQ permit for the construction of the sewer line extension.
2. 3 PI test done from approved locations and then the stamping engineer does the road calculations from the average of the results from the Modified AASHTO rigid industrial attached to the back of the drawing.
The City Planning Commission recommended approval on July 25, 2024.
EXHIBIT: Construction Plans
CPC Minutes 7-25-24
KEY ISSUES: None
FUNDING SOURCE: N/A
STAFF RECOMMENDED COUNCIL ACTION: Approve the offsite improvement construction plans for an extension to SW Gilbert Gibson Rd, water line, and sanitary sewer to serve Fisher 59 and future development within the Airport Industrial area, subject to the conditions listed.