ITEM TITLE:
Title
Consider approving Amendment No. 1 and Change Order No.1 with K&R Builders, Inc., on Engineering Project EN2205 - NE 29th Street Drainage Culvert and Appurtenances (M14-4) over Tributary to Wrattan Creek.
body
INITIATOR: Joseph Painter, P.E., Director of Engineering/City Engineer
STAFF INFORMATION SOURCE: Joseph Painter, P.E., Director of Engineering/City Engineer
BACKGROUND: On December 12, 2023, Council awarded construction contract in the amount of $617,913.90 to K&R Builders for Project EN2205-Construction of NE 29th St Drainage Culvert and Appurtenances (M14-4) over Tributary to Wrattan Creek to replace the existing CGMP with a 3-cell reinforced concrete box, and restoring the pavement that was supported by the pipes.
Amendment No. 1 and Change Order No. 1 accounts for the construction and the time required to mitigate and concrete encase a conflicting 10” sanitary sewer line; and weather days. This work will add $4,082.10 to the original contract amount making the new contract sum as $621,996.00, and will add 17 calendar days (11 weather days and 2 work days = equivalent 17 calendar days) to the contract making the new contractual end date as June 20, 2024.
EXHIBIT: Amendment No. 1 & Change Order No. 1 - Project EN2205
KEY ISSUES: N/A
FUNDING SOURCE: OWRB SRF Loan
STAFF RECOMMENDED COUNCIL ACTION: Approve Amendment No. 1 and Change Order No.1 with K&R Builders, Inc., on Engineering Project EN2205 - NE 29th Street Drainage Culvert and Appurtenances (M14-4) over Tributary to Wrattan Creek.