ITEM TITLE:
Title
Per the recommendation of the Streets and Bridges Committee, consider directing staff to initiate the bidding process for King Road and items 11 through 40 on the “On Target, On Time” street project list.
body
INITIATOR: Councilmember George Gill
STAFF INFORMATION SOURCE: Councilmember George Gill; Councilmember Allan Hampton
BACKGROUND: On January 19, 2024, the Streets and Bridges Committee met to discuss going on to bid for the milling and overlaying projects on King Road (listed as ASAP) and items 11 through 40 on the “On Target, On Time” street project list. At this time, the committee is recommending that staff initiate the bidding process for all 30 streets in one bid package.
EXHIBIT: “On Target, On Time” Street Project List
KEY ISSUES: N/A
FUNDING SOURCE: N/A
STAFF RECOMMENDED COUNCIL ACTION: Direct staff to initiate the bidding process for King Road and items 11 through 40 on the “On Target, On Time” street project list.